Daum

Middlesex, NY

 

Ellis Tract

Dryden, NY

 

Ellis Tract

Dryden, NY

 

Ellis Tract

Dryden, NY

 

Evans

Norwich, NY

 

Pasto

Spencer, NY

 

Pinney

Dryden, NY

 

Geneva Agricultural Station (2.8MW)

Geneva, NY
Ground-mounted solar array developed, financed and constructed in 16 months. Key development tasks included securing entitlements for project adjacent to a designated historic site, navigating complex local laws, petitioning and advising the state regulator on new interconnection methods.

 

Harford Farm (2.8MW)

Dryden, NY
Ground-mounted solar array developed and financed. Key development hurdles included working around special flora and fauna habitats, New York State-regulated wetlands, existing dairy farm operations and utility interconnection issues.

 

Human Ecology Building

Ithaca, NY

 

Klarman Hall

Ithaca, NY

 

Musgrave Farm (2.8MW)

Aurora, NY
Ground-mounted solar array developed and financed. Under construction. Key development tasks included overhauling local utility interconnection protocols.

 

Snyder Road Farm (2MW)

Ithaca, NY
Ground-mounted solar array constructed on a brownfield land parcel, adjacent to a regional airport, with large federally designated wetlands. Developed, constructed and financed in 15 months.